April 23, 2025
The Facilities and Asset Management department would like to inform the 51³ÉÈ˸£ÀûÍø community of two upcoming construction projects scheduled to take place from May through August.
Please review the details below, including expected impacts to campus areas.
Arts E Railing Replacement Project
Location: Arts E Building – 2nd and 3rd Floors
Scope of Work: Replacement of railings on the 2nd and 3rd floors in the Arts E building by the washrooms and elevator (corridors 2E21 and 3E27).
Expected Impacts:
DAWB Generator Exhaust Upgrade Project
Location: Exterior East Side of DAWB Building – Adjacent to FNCC Loading Dock
Scope of Work: Replacement of exterior generator exhaust venting pipes. The venting will be routed over the lower roof of the FNCC loading dock and adjacent East side of the DAWB building.
Expected Impacts:
Thank you for your patience and understanding as we complete these important facility upgrades.
Please follow and respect all signage and barriers that will be in place for this work.